Exeter Energy insists Riverside Valley Park only viable heat plant site but fails to explain Marsh Barton brownfield rejection
Company admits River Exe water source connection merely “potential” after 2036, incinerator connection only “possible” after 2030 and solar array “will not” meet plant electricity demand while statutory objections challenge Grace Road Fields plans.

Exeter Energy plant replaces rationale for Grace Road Fields location near River Exe with reliance on air source heat pumps
Developer nevertheless seeks planning permission to build in Riverside Valley Park, claiming public open space “not bound” by local plan policy, as scheme ambition and city council environmental leadership claims begin to drain away.

University study finds decarbonisation slowing as city council continues to pursue failing Net Zero Exeter 2030 plan
Exeter also set to miss national 2050 target on current trajectory while aviation, shipping and other excluded scope 3 greenhouse gas emissions mean annual city carbon footprint likely to be triple territorial total.