Trew’s Weir lies 500 metres downstream of Exeter Quay, just past the entrance to Exeter Ship Canal. It was built to maintain water levels in the quay and canal and named after John Trew, the engineer who constructed the canal’s first section in 1564-66.
The 72-metre weir has undergone numerous modifications and repairs over many years. It now includes fish and eel passes which were installed by the Environment Agency at its western end in 2010 and a bypass channel at its eastern end which marks the route of a previous mill off-take.
The maintenance of the passes is essential to the nationally-important salmon and trout-spawning migration route and European eels habitat provided by the River Exe.
At the same time, the weir holds an upstream water level three metres higher than the natural downstream level while protecting high-voltage power cables on the river bed which provide power to thousands of city centre residents and businesses.
Were it to collapse, upstream water levels would fall significantly, scouring the river bed and damaging the city centre power supply cables, emptying the canal – where boats would be grounded and the banks would be destabilised – and undermining the viability of businesses at the quay.
Resulting water flow increases would also have major impacts on the river bed, its banks and adjacent structures all the way upstream to Mill on the Exe and downstream to St James’ Weir at Salmon Pool, beside Duckes Meadow, which itself collapsed eight years ago.
Trew’s Weir. Image: Exeter City Council.
Exeter Civic Society had raised concerns about significant deterioration in the structural integrity of St James’ Weir in 2013 but neither Exeter City Council nor the Environment Agency would take responsibility for its upkeep because its ownership was difficult to prove.
The society pointed out that, should the weir be allowed to collapse, significant upstream consequences would follow. An Environment Agency-commissioned assessment also identified extensive upstream risks and concluded that a large breach was likely unless, at the very least, minimal repairs were carried out.
Repairs did not take place. When St James’ Weir subsequently collapsed in December 2018 the water level at Trew’s Weir fell by 1.5 metres, exposing the condition of its previously-submerged surface and raising concerns that it might also collapse.
Intrusive investigations followed. They found that Trew’s Weir is primarily constructed of gravel, sand and silt, retained by timber stakes and covered with stone blocks and a concrete crest. They also found voids in its structure which allow water to flow straight through, making its core susceptible to being washed away.
The Environment Agency’s initial response to the water level fall at Trew’s Weir was to install a £470,000 temporary extension to the fish pass, for which it is responsible. This was intended to enable salmon and trout to migrate upstream to their spawning habitats instead of being trapped below the weir, vulnerable to predation, by the newly-exposed drop.
The fish pass extension was installed in September 2019. It was only supposed to provide two years’ respite for the Environment Agency to consider what it called “long-term options” for St James’ Weir with the city council, which owns and is responsible for the rest of the Trew’s Weir structure.
The extension did not provide a pass for eels to ascend the weir, and subsequent water level changes and other factors have continued to delay or distract migrating fish below the weir.
The Environment Agency eventually allocated £2.9 million for Trew’s Weir remedial works – in 2025, seven years after St James’ Weir collapsed – to be carried out by the city council. When the council added the grant funding to its capital programme budget last December it said it expected the works to be completed in 2026.
The scheme design, however, had not been finalised. A presentation to Exeter Harbour Board which followed said the plans would involve rebuilding most of the weir. Sheet piles and a new watertight single-gradient concrete surface would be installed which would extend further downstream below the water level than the existing weir.
The plans also included a new, improved fish pass, a new eel pass at the eastern end of the weir and modifications to the bypass channel to reduce distracting water flows. Options for a portage over the weir for canoes and kayaks were also being considered, although this was described as the least critical component of the scheme.
The design was intended to have a minimum lifespan of at least 100 years, maintain upstream water levels irrespective of flow rates while minimising flood risk impacts, provide protective ducting for future National Grid high-voltage cable crossings and maintain fish migration routes and river and canal operations during delivery.
The works were to be carried out in two phases, between spring and autumn this year and next, using one of the council’s Haven Banks car parks as a compound. A public consultation on the proposals was to follow in January this year.
Without the works, the council engineer said, Trew’s Weir had a remaining lifespan of only 1-5 years.
Trew’s Weir replacement scheme outline, December 2025. Image: Exeter City Council.
The January public consultation did not take place, however. In February, the council said it would have to double the scheme budget to £5.9 million and that it would have to borrow £3.1 million on top of the Environment Agency grant to cover the costs.
In March it said that it was seeking Environment Agency help with the additional costs and was having to review the scheme design to consider flood risk projections, especially in scenarios in which river water levels rose to the top of the city’s flood defences. As a result, the city’s harbour board was told, the project was not expected to come forward until early 2027.
Then, at a harbour board meeting held this week, the council issued a “statement of progress”.
It said it had reassessed its previous plans and concluded, in January, that they did not “represent a deliverable or financially-feasible solution”. It had received revised project cost estimates of £12 million – twice as much as its already-doubled budget – and discovered that its design proposals would actually have increased flood risk during “more extreme river events”.
As a result, it said, it had “paused” further development work on the scheme.
Trew’s Weir visible structural defects. Image: Exeter City Council.
The council has since put together a revised scheme with a massively-reduced scope of works to cut project costs to £2 million.
It says the new scheme would retain the “overall geometry and hydraulic function” of the weir so it would have no impact on flood risk.
Instead of sheet piling and large concrete slabs, the new scheme would principally consist of injecting resin grout into the existing structure to reduce water ingress, with repointing and “additional localised repairs” to the weir surface, downstream wall and other masonry.
Its aim is to stabilise and strengthen the weir to make it “more resilient into the future”. It says doing so will not provide the “full 100-year” life of the previous design, but has not said how long it expects the new design to last instead.
It adds that the reduced budget and scope of works mean it cannot rebuild the fish pass – which it says is entirely the Environment Agency’s responsibility.
It says the new scheme could be delivered within the “previously-secured” £2.5 million budget, apparently relying on the approved Environment Agency grant. However it adds that it intends to seek external funding from DEFRA to “reduce the level of ECC capital expenditure required” – which seems to suggest that Environment Agency funding for the scheme may no longer be forthcoming.
The council’s new scheme is nevertheless still only at “concept sketch” stage, and the “meaningful public and stakeholder engagement” it says it intends to undertake will have to wait until the design has reached a “suitable level of detail”.
As it is aiming to complete the detailed design by early next year, before appointing contractors in spring 2027 and completing the works by next November, we might expect this consultation to take place sometime between now and the end of the year.